Whitehead Extension Project

Updated 25th January 2019

Over the next two years, work will continue to connect individual properties in Whitehead and will see approximately 8km of pipeline constructed each year, connecting 800 properties each year

2019 Construction Schedule Map

Overall Whitehead Infill Map

  • Whitehead Phase 1&2 works ongoing. A lane closure is in operation on the Belfast Road from Monday 21st January 2019 for approximately 2 weeks.
  • Phase 3 works are due to commence in February 2019
  • Phase 4 works are due to commence in late February 2019

Estimated project completion date: May 2019

*Please note, these are estimated timescales only and may be affected by ground conditions or other external factors. Please continue to check this page for regular updates to the programme*